Question: Use the following project info to answer. q , ( times are in weeks, costs in hundreds ) a . What is project duration and

Use the following project info to answer. q,(times are in weeks, costs in hundreds)
a. What is project duration and cost and critical path?(note there are no indirect costs)
b. How would you shorten the project by 1 week? Now what is the project duration, cost, and critical path?
c. How would you shorten the project again by 1 week? What is the project duration, cost, and critical path?
d. One more week..... how would you shorten the project by another week? What is the final project duration, cost, and critical path?
\table[[Activity,Normal-_,Crash-,Predecessor(s)],[Time,Cost,Time,Cost],[A,3,50,2,70,--],[B,5,60,3,180,A],[C,3,70,2,110,A],[D,10,50,--,-,A],[E,6,100,3,250,B],[F,7,90,4,390,c],[G,5,50,4,120,D, EF]]
 Use the following project info to answer. q,(times are in weeks,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!