Question: Use the following project information for Problems 1 and 2. Activity Time (weeks) Immediate Predecessor(s) Activity none A B B. A B D E F

Use the following project information for
Use the following project information for Problems 1 and 2. Activity Time (weeks) Immediate Predecessor(s) Activity none A B B. A B D E F G NA NA 3 4 2 5 4 3 2 2 C D E, F 1. Construct a network diagram using AON notation. 2. Using the network diagram constructed in Problem 1, (a) Calculate the completion time for the project. (b) Determine which activities are included on the critical path. ada