Question: Use the following project information. Optimistic Time Estimate(weeks) Activity A 2 B 2.5 C D E F G H I J 3 4 2 4

Use the following project information. Optimistic

Use the following project information. Optimistic

Use the following project information. Optimistic Time Estimate(weeks) Activity A 2 B 2.5 C D E F G H I J 3 4 2 4 6 4 2 Most Likely Time Estimates (weeks) 3 4 6 01 5 7 5 5 6 8 3 Pessimistic Time Estimates (weeks) LO 5 5 8 7 14 9 6 8 10 3 Immediate Predecessor(s) none A A B, C B, C D 0 HI Calculate the expected time for each of the project activities. (Round your answers to 2 decimal places, e.g. 1.75.) Expected Time Activity A B C D E F G H J IN