Question: Use the following to answer the questions for problem # 3 There are 3 paths on a project. Length Path A: 1 - 2 -

Use the following to answer the questions for problem #3
There are 3 paths on a project.
Length
Path A: 1-2-4-5-6
8+6+3+1=18
8+11+1=20
4+9+1=14
Path B: 1-2-5-6-,8+11+1=20
Path C: 1-3-5-6,4+9+1=14
a. Draw the diagram.
b. What is the earliest start, earliest finish, latest start, and latest finish for each
activity?