Question: Use the high low method to determine: the variable cost per unit, total fixed costs, and the total cost equation. Willis Inc. provided information for
Use the high low method to determine: the variable cost per unit, total fixed costs, and the total cost equation.
Willis Inc. provided information for costs of its delivery fleet: Total Cost $95,000 103,000 80,000 101,000 Month January February March April Miles 60,000 70,000 49,000 79,000
Step by Step Solution
There are 3 Steps involved in it
To use the highlow method we need to identify the highest and lowest activity levels and their corre... View full answer