Question: USE THE INFORMATION BELOW FOR THE FOLLOWING PROBLEM Asset (A) Asset (B) E(RA) = 14% E(RB) = 16% (A) = 13% (B) = 18% WA
USE THE INFORMATION BELOW FOR THE FOLLOWING PROBLEM Asset
(A) Asset (B)
E(RA) = 14% E(RB) = 16%
(A) = 13% (B) = 18%
WA = 0.4 WB = 0.6
COVA,B = 0.0024
What is the standard deviation of this portfolio?
1)10.0%
2)12.5%
3)14.4%
4)15.5%
5)16.0%