Question: Use the information below to answer the following question: The project manager is using PERT to determine what the probability is of completing the following

Use the information below to answer the following

Use the information below to answer the following question: The project manager is using PERT to determine what the probability is of completing the following project for various durations. Durations are in days. B -D E Task B D E Optimistic (a) 8 4 18 6 12 Most Likely Pessimistic (m) (b) 8 8 6 20 24 42 8 28 18 30 A What is the expected project duration? O a) 50 days Ob) 72 days O c) 53 days O d) 46 days e) 64 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!