Question: Use the information contained below to compress one - time unit per move using the least cost method.Reduce the schedule until you reach the maximum

Use the information contained below to compress one-time unit per move using the least cost method.Reduce the schedule until you reach the maximum crash point (crash duration) of the network.For each move identify what activity was crashed and the adjusted total cost.Activity IDSlopeMax crashtimeNormalTimeNormalCostCrashTimeCrashCostA $80.00210$408$200B$20.0027$805$120C$50.00211$509$150D$50.00216$10014$200E$30.0012$301$60F$0.0003$1503$150G$0.0002$502$50