Question: Use the information contained below to compress one time unit per move using the Main Content ethod. Answer questions 64 through 67. If you want

Use the information contained below to compress one time unit per move using the Main Content ethod. Answer questions 64 through 67. If you want to reduce the project the maximum amount it can be reduced, what will be the total project direct cost