Question: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash

Use the information contained below to compress

Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the crash cost. Activity Predecessor Normal Time Crash Cost Max Crash Time None 1 0 0 B 3 2 100 C A 4 1 50 D B 3 1 60 E C 4 2 70 F D, E 3 1 90