Question: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash


Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the adjusted total cost. Note: Crash point of the network is the point in which the duration cannot be reduced any further. Activity Crash Cost (Slope) Maximum Cr Time 20 1 1 B 60 2 40 1 D 0 0 E 50 3 F 100 3 Activity Crash Cost (Slope) Maximum Cr Time 20 1 B 60 2 40 1 D o 0 E 50 3 F 100 3 G 70 1 B E Initial project duration 19 5 6 F G 5 3 3 7 D 10x Total direct cost $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock