Question: Use the information contained below to compress one time unit per move using the least cost method. Recuce the schedule until you reach the crash



Use the information contained below to compress one time unit per move using the least cost method. Recuce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed, the adjusted total cost, and explain your choice if you have to choose between activities that cost the same. [12] Note: Crash point of the network is the point in which the duration cannot be reduced any further. Total Direct Normal Costs $610 Question No: 05 Completion Time: 21 Total Cost $610