Question: Use the information from Table 2 to estimate the mean and the standard deviation of the ORTOT. Use two decimal points for all of your

Use the information from Table 2 to estimate the mean and the standard deviation of the ORTOT. Use two decimal points for all of your calculations. Present your network diagram and the earliest and latest starting times as well as the earliest and latest finishing times of each activity. What is the critical path? What is your finding from the PERT analysis?

Table 2: Information for PERT Analysis

ActivityPersonnelDescriptionImmediate PredecessorOptimisticMost LikelyPessimistic
AAnesthesiologistTransport Patient 1 to PACUN/A222
BAnesthesiologistClean up and prepare for the next surgeryA293757
CSurgeonSurgeon preparation for next surgeryA71535
DSurgery RNRN preparation for next surgeryA203242
EScrub TechScrub Tech breaks down tasksA51015
FScrub TechSterile tasksG, E123037
GOrderly TeamOrderly taskA3715
HAnesthesia TechAnesthesia tasks for the next surgeryA152735
IPre-op RNPreop checklist for Patient 2B, C, D, F51020
JSurgeon and Surgery RNTransport patient 2 to ORI222

Step by Step Solution

3.42 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!