Question: Use the information from the following table: Cost Pool Total Cost Allocation Base Units A $120,000 # of purchase orders 2,000 B $85,000 # of
Use the information from the following table:
| Cost Pool | Total Cost | Allocation Base | Units |
| "A" | $120,000 | # of purchase orders | 2,000 |
| "B" | $85,000 | # of inspections | 5,000 |
| "C" | $120,000 | # direct labour hours | 24,000 |
| "D" | $75,000 | # machine hours | 15,000 |
A job was allocated $2,000 in cost from cost pool C. How many direct labour hours were used on this job?
a.
100
b.
1,000
c.
60
d.
400