Use the information from the following table: Cost Pool Total Cost Allocation Base Units A $120,000 #
Fantastic news! We've Found the answer you've been seeking!
Question:
Use the information from the following table:
Cost Pool | Total Cost | Allocation Base | Units |
"A" | $120,000 | # of purchase orders | 2,000 |
"B" | $85,000 | # of inspections | 5,000 |
"C" | $120,000 | # direct labour hours | 24,000 |
"D" | $75,000 | # machine hours | 15,000 |
Job #592 involved 25 purchase orders, 12 inspections, 150 direct labour hours, and 200 machine hours. How much manufacturing overhead cost will be assigned using activity-based costing?