Question: Use the information in the table below questions. Activity: A, B, C, D, E, F, G, H, I,J T2= 31, 28, 32, 18, 32, 55,
Use the information in the table below questions. Activity: A, B, C, D, E, F, G, H, I,J T2= 31, 28, 32, 18, 32, 55, 16, 23, 34, 17 Standard Deviation: 1, 4, 19, 4, 0, 4, 4, 27, 7.11, 9 Critical: Yes, No, No, Yes, No, Yes, No, Yes, No, No What is the estimated time for the project completion (days)? The estimate standard deviation for the critical path is (days)? Which task would be considered the riskiest task that could jeopardize a project completing on time? Focusing on the critical path, what is the probability of this project in completing in 120 days? How many days of the completion is 90%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
