Question: Use the information provided below to calculate the unit overheads cost using Activity Based Costing. INFORMATION The output of Project K of Turbo Limited is
Use the information provided below to calculate the unit overheads cost using Activity Based Costing.
INFORMATION The output of Project K of Turbo Limited is Product A and Product B and the company is keen on applying the principles of ABC costing. Relevant information pertaining to the two products for a given period appear below:
| | Product A | Product B |
| Output in units | 240 | 180 |
| Machine hours per unit | 7 | 5 |
| Direct materials | R100 | R80 |
| Direct labour cost per unit | R49 | R35 |
The two products are similar and are usually produced in production runs of 20 units and sold in batches of 10.
Currently the production overheads are absorbed by using a machine hour rate, and the total of the production overheads for the period are as follows:
The cost drivers to be used for the overhead costs are as follows:
| Machine department costs (rent, rates, depreciation and supervision) | 10 320 |
| Set-up costs | 5 040 |
| Stores receiving | 3 720 |
| Inspection/Quality control | 2 100 |
| Materials handling and dispatch | 4 620 |
The number of requisitions raised on the stores was 40 for each product and the number of orders executed was 42, each order being for a batch of 10 of a product
| Set up costs | Number of production runs |
| Stores receiving | Requisitions raised |
| Inspection/Quality control | Number of production runs |
| Materials handling/Dispatch | Orders executed |
Step by Step Solution
3.51 Rating (161 Votes )
There are 3 Steps involved in it
To calculate the unit overhead costs using Activity Based Costing ABC well distribute the total overheads to each product based on their activity usag... View full answer
Get step-by-step solutions from verified subject matter experts