Question: Use the information to crash one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the

Use the information to crash one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. What is the adjusted total cost after the crash point has been reached?Use the information to crash one-time unit per

Act. Crash Cost (slope) Maximum Crash Time Normal Time Normal Cost A 100 1 2 150 B 80 1 3 100 60 1 2 200 D 40 1 5 200 E 40 2 5 200 F 40 2 3 150 G 20 1 5 200 H 0 0 1 200 C F 2 3 Project duration 16 B 3 H A D G 1x 2 5 5 E Total direct cost $1,400 5