Question: Use the Normal time given in the table below to reduce the project by 6 days. What is the added cost? Show the activity/activities that
- Use the Normal time given in the table below to reduce the project by 6 days. What is the added cost? Show the activity/activities that need to crash for each day. What activity to crash for the 1st day, what activity to crash for the 2nd day, and so forth.
|
|
|
| Time (days) | Activity cost (S) | |||
| Activity | Description | Predecessor | Normal | Crash | Normal | Crash | |
| a | Excavation, pour footers | none | 6 | 4 | $10 | 20 | |
| b | Lay foundation | a | 5 | 3 | $22 | 28 | |
| c | Frame and roof | b | 5 | 4 | $15 | 22 | |
| e | Sewer (floor) drains | b | 3 | 2 | $21 | 25 | |
| f | Install insulation | c | 5 | 4 | $25 | 30 | |
| g | Pour basement floor | e | 5 | 3 | $12 | 18 | |
| i | Install windows | f | 4 | 3 | $20 | 22 | |
| J | Rough electrical wiring | f | 3 | 2 | $20 | 20 | |
| k | Install furnace | c,g | 8 | 5 | $11 | 23 | |
| l | Exterior brickwork | i | 8 | 6 | $16 | 28 | |
| m | Install plasterboard | j,k | 10 | 8 | $18 | 26 | |
| n | Roof shingles | I | 4 | 3 | $23 | 29 | |
| o | Attach gutter | n | 5 | 2 | $25 | 31 | |
| p | Grading | o | 7 | 3 | $12 | 16 | |
| q | Lay subflooring | m | 5 | 4 | $17 | 22 | |
| r | Lay driveway | p | 8 | 6 | $20 | 30 | |
| t | Kitchen, sink, appliances | q | 8 | 4 | $18 | 28 | |
| v | Painting | t | 8 | 6 | $15 | 24 | |
| w | Finish wood floor | v | 8 | 6 | $25 | 34 | |