Question: Use the Northwest Corner method result as the starting point and solve for the optimal solution using the Stepping-Stone method. Show all steps and all
- Use the Northwest Corner method result as the starting point and solve for the optimal solution using the Stepping-Stone method.
- Show all steps and all calculations when doing the Stepping-Stone method.
Plants Supply Destination Demand
Kansas City 35 Chicago 30
Omaha 50 St. Louis 65
Des Moines 50 Cincinnati 40
Total 135 tons Total 135 tons
Transport cost from Plants to Destinations ($/ton) | |||
| Plants | Chicago | St. Louis | Cincinnati |
| Kansas City Omaha Des Moines | $4 6 8 | 3 7 2 | 3 6 5 |
I think I understand the northwest corner method, but the stepping stone method is confusing me. Please help me understand it.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts