Question: Use the project flow diagram given in the previous question. Assume the time unit is measured in days. Question: Starting these activities one day late

Use the project flow diagram given in the previous question. Assume the time unit is measured in days.
Question: Starting these activities one day late will delay the project completion by at least one day.
Group of answer choices
Activities I and F
Activities C and E
Activities B and J
Activities A and G