Question: Use the provided template to create your network diagram, answer the questions, and upload your file. Click on the blue file name to download the
Use the provided template to create your network diagram, answer the questions, and upload your file. Click on the blue file name to download the PPT document with the schedule network diagram analysis: - Question 21 Worksheet B - Schedule Network Diagram.pptx -
OR
You can draw the network diagram manually on paper, answer questions on the same page, take a picture of your work and upload your file. (If you encounter technical challenges wile uploading the file, you may also email your work to the course instructor.) Show all your work.
Description:
a) Given the activities, predecessors, and durations displayed in the precedence table below, draw a network diagram.
b) Identify all network diagram pathways and their durations.
c) Identify the critical path(s).
d) Provide the definition for critical path
e) How long will it take to complete the project?
f) What is the float (slack) time for activity I?
g) What is the float (slack) time for activity D?
h) What is the float (slack) time for activity A?
i) What is the float (slack) time for activity E?
| Activity | Predecessor Activity | Duration in Days |
| A | F | 4 |
| B | I | 4 |
| C | K | 3 |
| D | E & B | 3 |
| E | None | 4 |
| F | I & L | 1 |
| G | A & C | 3 |
| H | J | 3 |
| I | None | 2 |
| J | M | 2 |
| K | L | 2 |
| L | None | 3 |
| M | None | 6 |