Question: Use the schedule data in the table below to answer the question below it. All of the tasks are within the detailed planning period. All

Use the schedule data in the table below to answer the question below it. All of the tasks are within the detailed planning period. All relationships are finish-to-start unless otherwise noted. Task Name Duration Start Finish Predecessors Successors A 10 days Mon 9/18/17 Fri 9/29/17 B B 14 days Mon 10/2/17 Thu 10/19/17 A C C 22 days Fri 10/20/17 Moni 11/20/17 B DE D 11 days Tue 11/21/17 Tue 12/5/17 C F