Question: Use the Table 1 ( Columns 1 , 2 , and 4 to answer the following questions: i . Using Network analysis determine the Critical

Use the Table 1(Columns 1,2, and 4 to answer the following questions:
i. Using Network analysis determine the Critical Path of the Project
ii. Calculate the planned duration on the project in months
iii. Identify any non-critical tasks and the floats/slack time on each task
iv. Determine the Total Float for each Path.
TABLE 1: Network Activities
ACTIVITY
(1)
PREDECESSO
R
(2)
OPTIMISTIC
TIME
(Months)
(3)
MOST
LIKELY
TIME
(Months)
(4)
PESSIMISTIC
TIME
(Months)
(5)
A -579
B A 141516
C B 232527
D B 131517
E B 283032
F C,D 81011
G E,F 101214
H G 357
I H 246

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!