Question: Use the table below to answer the following question(s) using the standard Solver. Coppell Services contracts with outsourcing partners to handle various customer service functions.
Use the table below to answer the following question(s) using the standard Solver. Coppell Services contracts with outsourcing partners to handle various customer service functions. Based on a study of call volumes provided by one of the firm's partners, the minimum number of staff needed for each hour of the day is as follows:
| Hour | Minimum Staff Required |
| 8-9 | 6 |
| 9-10 | 10 |
| 10-11 | 12 |
| 11-noon | 10 |
| noon-1 | 8 |
| 1-2 | 16 |
| 2-3 | 15 |
| 3-4 | 20 |
| 4-5 | 15 |
Mr. Coppell hires 6 permanent employees and wants to staff the remaining requirements using part-time employees who work 4-hour shifts (four consecutive hours starting as early as 8 A.M. or as late as 1 P.M.). How many part-time employees are present in the 8-9 time slot?
9
14
6
4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts