Question: Use the table below to plot the resource load chat and answer the questions below. 1.What is Activity G's updated Start Time (ES) and Revised

Use the table below to plot the resource load chat and answer the questions below.

1.What is Activity G's updated Start Time (ES) and Revised Slack?

Start 8; Slack 0

Start 12; Slack - 4

Start 12; Slack 0

Start 8; Slack -4

2.Based on the resource constraint, the project will finish:

On time - day 12

Two days early - day 10

Two days late - day 14

Four days late - day 16

3. Activity F is scheduled after Activity E, even though, based on revised start times, they are both scheduled to start in time period 7, because F can only start once E is complete

E's duration is less than that of F

E's slack is smaller than that of F

E precedes F in the alphabet

4. Which activities are critical? All activities are now critical

All activities except A and C are critical

Only activities B, D, and E are critical

As two days of slack can be added to activity F, all activities except F are critical

Use the table below to plot the resource load

Use the following heuristics: Minimum slack Smallest duration Lowest identification number 2 B 3 2 2 2 Legend ESID EF 6 E 8 8 G 10 020 6020 628 8 2 10 SL RES SL 4 15 LS DU LE 0 A 2 0 20 5 D 6 020 51/6 022 2 C 5 0 2 0 235 6 F 9 1 1 1 7/3 10 10 H 12 1020 10 2 12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!