Use the table below to plot the resource load chat and answer the questions below.
1.What is Activity G's updated Start Time (ES) and Revised Slack?
Start 8; Slack 0
Start 12; Slack - 4
Start 12; Slack 0
Start 8; Slack -4
2.Based on the resource constraint, the project will finish:
On time - day 12
Two days early - day 10
Two days late - day 14
Four days late - day 16
3. Activity F is scheduled after Activity E, even though, based on revised start times, they are both scheduled to start in time period 7, because F can only start once E is complete
E's duration is less than that of F
E's slack is smaller than that of F
E precedes F in the alphabet
4. Which activities are critical? All activities are now critical
All activities except A and C are critical
Only activities B, D, and E are critical
As two days of slack can be added to activity F, all activities except F are critical