Question: Use the tabulated data and answer the questions that follow. Use two - decimal accuracy for all estimates. Time estimate ( days ) Activity Activity

Use the tabulated data and answer the questions that follow. Use two-decimal accuracy for all estimates.
Time estimate (days)
Activity Activity predecessor a m b
A -467
B A 357
C A 369
D A 369
E B, C 367
F B, C 359
G F 469
H D, E, F 567
a. Draw the network and show the earliest start, earliest finish, latest start, latest finish, and slack.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project i) within 22 days and ii) between 24 and 26 days?
e. If the project's completion probability is 0.70, within how many days will you complete the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!