Question: USE these answer formats. A number is represented by n i.e. 5 Start and finish is represented by startspacefinish i.e. 6 12 Pathname and duration

USE these answer formats.

A number is represented by n i.e. 5

Start and finish is represented by startspacefinish i.e. 6 12

Pathname and duration are entered as 'pathnamespacedurationlength' i.e. abc 23

If no answer exists enter no answer

If the answer is yes enter yes

If the answer is no enter no

A project has a listing of tasks and durations. A4 is followed by D3 and B5. E4 follows D and B. C6 follows B. F5 follows E. G7 follows F and C.

Use a PDM network diagram to answer the questions given.

Answer the following questions. Each answer field gets ONE answer.

  1. Name the paths and their durations.
  2. Using the backward pass what are the start and finish days for task D?
  3. Using the backward pass what are the start and finish days for task C?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!