Question: Use this info for questions 1 through 4. Determine the lowest cost plan for crashing this project. What is the expected project duration before crashing
Use this info for questions 1 through 4.
Determine the lowest cost plan for crashing this project.
What is the expected project duration before crashing any activities?
| Activity | Normal Time | Possible Crashes | Crash Cost Per Day |
| A | 6 | 1 | 135 |
| B | 11 | 3 | 40 |
| C | 13 | 3 | 75 |
| D | 9 | 2 | 55 |
| E | 8 | 3 | 45 |
| F | 5 | 1 | 40 |
Flag question: Question 2
Question 22 pts
What is the cost of the first crash?
Flag question: Question 3
Question 32 pts
What is the cost of the sixth crash?
Flag question: Question 4
Question 42 pts
What is the total cost of crashing this project by seven periods?
Flag question: Question 5
Question 52 pts
Use this info for questions 5 through 8.
Determine the lowest cost plan for crashing this project.
What is the expected project duration before crashing any activities?
| Activity | Norm Time | Norm Cost | Crash Time | Crash Cost |
| A | 4 | 2500 | 2 | 6400 |
| B | 7 | 4000 | 6 | 4600 |
| C | 4 | 3000 | 2 | 4400 |
| D | 3 | 2000 | 2 | 3000 |
| E | 9 | 3600 | 3 | 7500 |
| F | 4 | 2000 | 1 | 6500 |
| G | 2 | 2000 | 2 | 2000 |
Flag question: Question 6
Question 62 pts
What is the cost of the third crash?
Flag question: Question 7
Question 72 pts
What is the cost of the fourth crash?
Flag question: Question 8
Question 82 pts
What is the total cost of reducing this project's duration by six periods?
Flag question: Question 9
Question 92 pts
Use this info for questions 9 through 13.
Chucks Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $250 for each week his yacht is late. Determine the lowest cost plan for crashing this project.
Note: All numbers are in thousands, but keep them that way (i.e., don't enter the last three zeros).
What is the expected project duration before crashing any activities?
| Activity | Immediate Predecessor | Normal Time (weeks) | # Possible Crashes | Crash Cost Per Week |
| J | - | 10 | 1 | 175 |
| K | J | 8 | 2 | 45 |
| L | J | 5 | 2 | 60 |
| M | K | 4 | 2 | 20 |
| N | L | 6 | 2 | 55 |
| P | M, N | 5 | 2 | 265 |
| Q | P | 7 | 1 | 70 |
| Y | P | 8 | 2 | 35 |
| Z | Q | 6 | 1 | 95 |
Flag question: Question 10
Question 102 pts
What is the cost of the fourth crash?
Flag question: Question 11
Question 112 pts
What is the cost of the fifth crash?
Flag question: Question 12
Question 122 pts
What is the total cost of all crashes that should be done to minimize costs?
Flag question: Question 13
Question 132 pts
How much should be spent on penalties?