Question: Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.90;

Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.90; actual, $2.03 Standard yards per unit: standard, 4.74 yards; actual, 5.17 yards Units of production: 9,300 Calculate the direct materials quantity variance.

a. $7,598.10 unfavorable

b. $8,117.97 favorable

c. $7,598.10 favorable

d. $8,117.97 unfavorable