Question: Use this information to draw a network diagram and answer Questions 12-13. What is the expected duration of this project? Activity Immediate Predecessor Time A
Use this information to draw a network diagram and answer Questions 12-13. What is the expected duration of this project? Activity Immediate Predecessor Time A - 6 B - 3 C A, B 5 D B 6 E C, D 15 F E 9