Question: Use your master production schedule in Table 1 and your MRP schedule for subassembly A to develop a material requirement plan ( MRP ) for

Use your master production schedule in Table 1 and your MRP schedule for subassembly A to
develop a material requirement plan (MRP) for component C using the lot size of 100 units
ordering policy.
Week 12345678
C
Lead Time: 2 weeks; On Hand: 45 units; Lot Size: 100 units;
Scheduled Receipts: 100 units in Week 1 and 100 units in Week 2
Gross Requirement
Scheduled Receipts
Projected On Hand
Net Requirements
PO Receipts
PO Releases
\table[[Week,Forecast,\table[[Customer],[Orders]],\table[[Projected],[On-Hand I],[nventory]],\table[[Net Inventory],[Before MPS]],MPS Start,MPS Receipt,\table[[Pvailable-to-],[nventory]]],[1,45,42,116,119,119,169,77],[2,45,38,231,238,238,288,200],[3,50,51,237,236,236,286,185],[4,60,356,251,276,276,326,241],[5,60,20,306,346,346,396,326],[6,50,15,381,416,416,466,401],[7,50,10,456,496,496,546,486],[8,45,45,501,501,501,551,456]]
 Use your master production schedule in Table 1 and your MRP

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!