Question: User Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource 1 has a processing time of 3 minutes
User
Consider a process consisting of three resources. Assume there exists unlimited demand for the product.
Resource has a processing time of minutes per unit.
Resource has a processing time of minutes per unit.
Resource has a processing time of minutes per unit.
The three resources are staffed by different workers individually. The flow diagram is shown above.
what is the capacity of resource what is the bottle neck in the process? what is the utilization of resource how long does it take the process to produce units starting with an empty system, assuming this is a worker paced process?