Question: Using Agile Estimation method from lecture 7, create an Agile sizing and planning including Value for the Buck Score. Assume the team can complete 50
Using Agile Estimation method from lecture 7, create an Agile sizing and planning including Value for the Buck Score. Assume the team can complete 50 story points per Sprint.
Create User Story matrix.
How many sprints are required to complete the project?
Detail what user stories will be completed in each iteration in order of priority.
Build Roof - SP 49 - VP - 150
Swimming Pool - SP 60 - VP - 3
Decorate - SP 12 - VP -151
Carpets - SP 15 - VP - 90
Heating - SP 53 - VP 130
Build Walls - SP 52 - VP 88
Sheetrock - SP 40 - VP 87
Electrical - SP 20 - VP 143