1. The following information is given for an information systems project:
There are ten total tasks, named AJ.
Tasks A, B, and H have durations of two days.
Tasks C, E, I, and J have durations of three days.
Tasks D, F, and G have durations of one day.
Tasks A, B, and D can be conducted in parallel.
Task C must precede task B.
Tasks A and F must precede Task E.
Task E must precede Task G.
Tasks B and D must precede Tasks H and I, respectively.
Tasks G, H, and I may be conducted in parallel.
Tasks G, H, and I precede Task J.
1a. Draw a Precedence Diagram (PDM) for the project, based on the information given.
1b. Draw an Arrow Diagram (ADM) for the project, based on the information given.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!