Question: Using any software 1 . The following information is given for an information systems project: There are ten total tasks, named A J . Tasks
Using any software
The following information is given for an information systems project:
There are ten total tasks, named AJ
Tasks A B and H have durations of two days.
Tasks C E I, and J have durations of three days.
Tasks D F and G have durations of one day.
Tasks A B and D can be conducted in parallel.
Task C must precede task B
Tasks A and F must precede Task E
Task E must precede Task G
Tasks B and D must precede Tasks H and I, respectively.
Tasks G H and I may be conducted in parallel.
Tasks G H and I precede Task J
a Draw a Precedence Diagram PDM for the project, based on the information given.
b Draw an Arrow Diagram ADM for the project, based on the information given.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock