Question: Using Blank MRP sheets Create a level loaded (discreet, with no remnants) plan for XYZs based on a MPS of 40 per week (plan must

Using Blank MRP sheets
Create a level loaded (discreet, with no remnants) plan for XYZs based on a MPS of 40 per week (plan must be a minimum of 8 weeks).level 0 MPS
Create and complete an MRP plan for each item in the product tree
Inventory Lead-time and Lot Size Information: XYZ A B D E F G H 2 Lead Time 1 2 1 1 1 2 2 2 2 Projected On Hand 93 125 32 92 520 391 68 || 500 1256 Lot Size LFL LFL 2010 LFL 100 200 100 50 Scheduled Receipts 50 0 o o O 0 0 0 0 O 100 0 Safety Stock 10 50 25 **Note** all scheduled receipts are in week 1