Question: Using customer demand data, a company estimates it needs to produce items at a takt time of 38 seconds per item. Based on the operator

Using customer demand data, a company estimates it needs to produce items at a takt time of 38 seconds per item. Based on the operator loading chart shown (as is, without balancing), this process can meet takt time. TRUE OR FALSE?Using customer demand data, a company estimates

Operator Loading Chart 45 42 40 38 34 35 30 25 Cycle Time (Seconds per item) 20 ili 15 10 5 0 Station A Station B Station C Station D