Question: Using discrete available - to - promise ( ATP ) logic, calculate the master production schedule ( MPS ) for the following conditions. table

Using discrete available-to-promise (ATP) logic, calculate the master production schedule (MPS) for the following conditions.
\table[[,,Period],[,On hand,1,2,3,4,5,],[Forecast,,20,18,25,15,12,],[Orders,,6,4,8,0,3,],[Projected available balance,15,,,,,,],[Available-to-promise (discrete),,,,,,,],[Master production schedule,,,,,,,],[Lot size =25, Safety stock =10,]]
How many units are available-to-promise (discrete) in period 3?
13
17
20
25