Question: Using Earned Value Analysis and the information in the Table of Dependencies and Field Report provided below: 1.1 Calculate the following project control metrics: 1.1.1.

Using Earned Value Analysis and the information in the Table of Dependencies and Field Report provided below:

1.1 Calculate the following project control metrics:

1.1.1. ACWP- Actual Cost of Work Performed (TWO marks)

1.1.2. BCWP- Budgeted Cost of Work Performed (TWO marks)

1.1.3. BCWS Budgeted Cost of Work Scheduled (TWO marks)

1.1.4. CPI Cost Performance Index (TWO marks)

1.1.5. CV- Cost Variance (TWO marks)

1.1.6. SPI Schedule Performance Index (TWO marks)

1.1.7. SV- Schedule Variance (TWO marks)

1.2 Is the project within budget and within schedule? Briefly explain why? (THREE marks)

1.3 If the project is not within budget and or within schedule, identify one measure you will recommend to get the project under control and

briefly explain why?

Activity

Predecessor

Duration (days)

Cost/Day

Total Cost $

A

none

3

400

1200

B

A

4

500

2000

C

B

4

500

2000

D

B

3

300

900

E

D

4

200

800

Field Report at end of day 10:

Activity

Actual % Complete

Incurred Cost

A

100

1200

B

100

2000

C

50

1200

D

33

400

E

0

0

Formulas:

CPI = BCWP/ACWP

CV = BCWP-ACWP

SPI = BCWP/BCWS

SV= BCWP-BCWS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!