Question: Using Earned Value to Determine Status Jennifer turned in her status report for the newly approved mailing activities. She feels that her pieces are on


Using Earned Value to Determine Status Jennifer turned in her status report for the newly approved mailing activities. She feels that her pieces are on track with nothing for you to worry about. She reports the following information for the critical path tasks: Task Budgeted |Actual Percent Estimate Planned Planned Actual Projected Planned Actual work ! work! work to start end start end date Resource Resource cost cost complete complete date date date Utilization Utilization to date A 120 60 30% 90 hours March June 15 March June 15 25% 30% hours / hours / $900 15 30 $1200 / $600 120 50 30% 60 hours April 1 May 15 April May 30 50% 30% hours / hours / $600 8 $1200 / $500