Question: USING EXCEL SOLVER - I would like to learn how to do this so if you can do this in solver, I would appreciate it.

USING EXCEL SOLVER - I would like to learn how to do this so if you can do this in solver, I would appreciate it.

Doug Casey is in charge of planning andcoordinating next spring's sales management training program for his company. Doug listed the following activity information for this project:

Time (weeks) Immediate Activity Description Predecessor Optimistic Most Probably Pessimistic A Plan Topic - 1.5 2.0 2.5 B Obtain Speakers A 2.0 2.5 6.0 C List meeting locations - 1.0 2.0 3.0 D Select location C 1.5 2.0 2.5 E Finalize speaker travel plans B,D 0.5 1.0 1.5 F Make final check with speakers E 1.0 2.0 3.0 G Prepare and mail brochure B,D 3.0 3.5 7.0 H Take reservations G 3.0 4.0 5.0 I Handle last-minute details F,H 1.5 2.0 2.5 a. Draw a project network b. Prepare an activity schedule c. What are the critical activities and what is the expected project completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!