Question: Using figure 6 - 2 , what is your Projected Completion costs if the To Date Quantities changed from 1 2 4 to 1 5

Using figure 6-2, what is your Projected Completion costs if the To Date Quantities changed from 124 to 150 and the To Date Expended Costs changed from $179 to $225?
Figure 6-2 Example of a Labor Cost Report
LABOR COST REPORT EXAMPLE
PROJECT NAME: Big Office Building
PROJECT NUMBER: 2015-012
\table[[CODE,DESCRIPTION,QUANTITIES,UNIT,EXPENDED COST,\table[[BUDGET],[TOTAL]],UNIT COST,PROJECTED],[BUDGET,WEEK,TO DATE,WEEK,TO DATE,BUDGET,WEEK,TO DATE,COMPLETION,GAIN/LOSS],[035300.1000,Wall Forms,1,120,60,124,Sqft,574,$179,$3,595,$3.21sqf,S1.23sqn,$1,44/sqft,$1,613,$1,982
 Using figure 6-2, what is your Projected Completion costs if the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!