Question: Using Johnson's nule for 2-machine scheduling. the secuence is: Six jobs are to be processed through as two-step operation. The first operation involves sanding, and

Using Johnson's nule for 2-machine scheduling. the secuence is: Six jobs are to be processed through as two-step operation. The first operation involves sanding, and the second imolves painting. Proce 