Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and

Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Scheduled Order Job 1 Operation Operation Job 1 (hours) 2 (hours) N 4 8 10 11 TIMOODD 4 14 14 12 6 For the schedule developed using Johnson's rule, the total length of time taken to complete the six . .. jobs (including the 2nd operation) = ] hours (enter your response as a whole number)