Question: Using Johnson's Rule, select the optimal sequence from the options below: a. CDEAB b. EDACB c. ABCDE d. BAEDC What is the make-span for sequence

Using Johnson's Rule, select the optimal sequence from the options below:
a. CDEAB
b. EDACB
c. ABCDE
d. BAEDC
What is the make-span for sequence identified in the previous question?
What is the total idle time?
What steps could be taken to reduce the idle time in this schedule?
Use Johnson's rule to obtain the sequence that minimizes the make-span for the jobs shown below through work centre 1 and work centre 2 Job Time (in Minutes) Job Work Centre 1 Work Centre 2 A 5 7 B 1 4 C 8 4 D 15 19 E 11 17Step by Step Solution
There are 3 Steps involved in it