Question: Using Microsoft Project, set up the network and determine the critical path for phase 1 of the Whistler Ski Resort project. The project workweek will

Using Microsoft Project, set up the network and determine the critical
path for phase 1 of the Whistler Ski Resort project. The project
workweek will be five days (MF).
Whistler Ski Resort Project
Given the fact that the number of skiing visitors to Whistler, B.C.,
Canada, has been increasing at an exciting rate, thanks to the 2010
Winter Olympics, the Whistler Ski Association has been considering
construction of another ski lodge and ski complex. The results of an
economic feasibility study just completed by members of the staff show
that a winter resort complex near the base of Whistler Mountain could be
a very profitable venture. The area is accessible by car, bus, train, and air.
The board of directors has voted to build the 10-million-dollar complex
recommended in the study. Unfortunately, due to the short summer
season, the complex will have to be built in stages. The first stage (year
1) will contain a day lodge, chair lift, rope tow, generator house (for
electricity), and parking lot designed to accommodate 400 cars and 30
buses. The second and third stages will include a hotel, an ice rink, a
pool, shops, two additional chair lifts, and other attractions. The board
has decided that stage one should begin no later than April 1 and be
completed by October 1, in time for the next skiing season. You have
been assigned the task of project manager, and it is your job to coordinate
the ordering of materials and construction activities to ensure the
projects completion by the required date.
After looking into the possible sources of materials, you are
confronted with the following time estimates. Materials for the chair lift
page 203
and rope tow will take 30 days and 12 days, respectively, to arrive once
the order is submitted. Lumber for the day lodge, generator hut, and
foundations will take 9 days to arrive. The electrical and plumbing
materials for the day lodge will take 12 days to arrive. The generator will
take 12 days to arrive. Before actual construction can begin on the
various facilities, a road to the site must be built; this will take 6 days. As
soon as the road is in, clearing can begin concurrently on the sites of the
day lodge, generator house, chair lift, and rope tow. It is estimated that
the clearing task at each site will take 6 days, 3 days, 36 days, and 6 days,
respectively. The clearing of the main ski slopes can begin after the area
for the chair lift has been cleared; this will take 84 days.
The foundation for the day lodge will take 12 days to complete.
Construction of the main framework will take an additional 18 days.
After the framework is completed, electrical wiring and plumbing can be
installed concurrently. These should take 24 and 30 days,
respectively. Finally, the finishing construction on the day
lodge can begin; this will take 36 days.
Installation of the chair lift towers (67 days) can begin once the site is
cleared, lumber delivered, and foundation completed (6 days). Also,
when the chair lift site has been cleared, construction of a permanent road
to the upper towers can be started; this will take 24 days. While the
towers are being installed, the electric motor to drive the chair lift can be
installed; the motor can be installed in 24 days. Once the towers are
completed and the motor installed, it will take 3 days to install the cable
and an additional 12 days to install the chairs.
Installation of the towers for the rope tow can begin once the site is
cleared and the foundation is built and poured; it takes 4 days to build the
foundation, pour the concrete, and let it cure and 20 days to install the
towers for the rope tow. While the towers are being erected, installation
of the electric motor to drive the rope tow can begin; this activity will
take 24 days. After the towers and motor are installed, the rope tow can
be strung in 1 day. The parking lot can be cleared once the rope tow is
finished; this task will take 18 days.
The foundation for the generator house can begin at the same time as
the foundation for the lodge; this will take 6 days. The main framework
for the generator house can begin once the foundation is completed;
framing will take 12 days. After the house is framed, the diesel generator
can be installed in 18 days. Finishing construction on the generator house
can now begin and will take 12 more days.
Assignment
1. Identify the critical path on your network.
2. Can the project be completed by October 1?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!