Question: Using only approved changes to update the project plan and project documents helps to______? Group of answer choices Maintain the integrity of baselines Minimize risk
Using only approved changes to update the project plan and project documents helps to______?
Group of answer choices
Maintain the integrity of baselines
Minimize risk
Inflate production times
Maintain WBS