Question: Using only the factors provided in this table below ( do not use excel, a scientific calculator, know the correct factor to use) Interest is

Using only the factors provided in this table below (do not use excel, a scientific calculator, know the correct factor to use)

Interest is 6% per period

Periods

FV of $1

PV of $1

FVA of $1

PVA of $1

1

1.0600

.9434

2.0600

0.9434

2

1.1236

.8900

3.1836

1.8334

3

1.1910

.8396

4.3746

2.6730

4

1.2625

.7921

5.6371

3.4651

5

1.3382

.7473

6.9753

4.2124

Company is considering a project that has estimated annual net cash flows of $18030 for four years and is estimated to cost $57810. The salvage value at the end of project is expected to be $5830. Fowlers cost of capital is 6 percent. The net present value of the project is $_______

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock