Question: Using PERT, calculate the time it takes for a task with the following information: Pessimistic time = 5 hours, Optimistic time = 2 hours, Most

Using PERT, calculate the time it takes for a task with the following
information: Pessimistic time=5 hours, Optimistic time=2 hours, Most likely
time=5 hours. The answer is: