Question: Using Program Evaluation Review Technique identify the critical activities and prepare a report determining the earliest and latest activity times, activity slack, critical path, duration

Using Program Evaluation Review Technique identify the critical activities and prepare a report determining the earliest and latest activity times, activity slack, critical path, duration for the project and the probability of completing the project.

Given the following details of the activities in a project with the time estimated in days, using PERT answer the following questions:

Activity

Precedence

Activities

Optimistic

Most

Probable

Pessimistic

A

---

2

5

6

B

---

1

3

7

C

---

6

8

10

D

A

5

10

14

E

A

3

4

5

F

A, B

8

9

12

G

C

4

6

8

H

C

2

7

9

I

E, F, G

5

7

12

J

H

12

13

14

K

D, J

2

3

4

  1. Draw the network of the project. What are the critical path activities?
  2. What is the expected time to complete the project?
  3. What is the probability the project will take more than 32 days to complete?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!